Lexington and Astoria-Broadway were pushed to the 2025-2029 Capital Plan. The Fulton Line from High Street to Euclid Avenue (in addition to that entire interlocking area surrounding Jay Street) was awarded a contract for this capital program that were in. And like @R32 3838 said, the IND have the oldest Signals in the system so given that Ridership is no longer the priority, it makes sense to replace the oldest Signals First. As for every other line, they’re all planned but Considers them low priority atm so you won’t be seeing them anytime soon, although Plans are Subject to change at any moment.
Technically you could overlay CBTC onto the existing fixed-block System but it won’t be Operational until you have the Enough Rolling Stock Equipped with CBTC.
Contractors installed the Wrong Track Ties so they had to go back and redo it.
But yea, the CBTC Schedule is looking like this at the moment:
Complete:
- Canarsie
- Flushing
- Queens Blvd West (50/8th to UT)
Under Construction:
- Culver (Church Av to West 8th) (Delayed due to Contractor Error)
- 8th Avenue (59 to High St)
- Queens Blvd East (UT to 179th) (Archer Avenue Branch postponed)
Contract Awarded:
- Crosstown+Culver North
- Fulton Street
- 63rd Street+6th Avenue (21st to York St)
Postponed to 2025-2029 Capital Program:
- Lexington Avenue (149th-Nevins)
- Astoria+Broadway
And then of course there’s the Fast Forward Plan, which most lines on here are a part of, I’m not sure how committed to it the still is to that but I hope they can pick up the pace soon.