Dulles Corridor Metrorail Project progress update e-mail 08 16 2011


Sand Box John

Recommended Posts

273.jpg

Tying In The Orange Line: Double crossovers just before installation over Labor Day weekend looking westbound in the median of Interstate 66.

Photo by Stephen Barna, Dulles Corridor Metrorail Project

 

Crossovers Installed for Tie-in to Existing Orange Line

 

Metro Service Shutdowns Between East and West Falls Church Stations Key to Construction Progress[/b]

 

One of the most challenging tasks in building the Dulles Corridor Metrorail Project is connecting the new line with Metro's existing Orange Line near the junction of two of Northern Virginia's most heavily traveled roads-- Interstate 66 and the Dulles Connector Road (Route 267).

 

For many months, crews have been installing track and performing other operations necessary to make this connection possible. Crews have been working adjacent to existing tracks and moving trains, performing intricate tasks and sometimes causing Metro to shut down train service between the West Falls Church and East Falls Church Metro stations to make sure that workers can do their jobs safely. The service disruptions must be coordinated with Metro and take place during low traffic times-weekends and holidays. The next outage will take place over the Columbus Day weekend.

 

Crews use each closing to perform a different task in tying the new line to the operating Orange Line

 

271.jpg

Into Place: Crews lift and place a double crossover panel where existing tracks have been removed.

Photo by Stephen Barna, Dulles Corridor Metrorail Project

 

Cables, Crossovers:

 

In order to connect the new and the existing rail line, the retaining walls around the existing track had to be widened. Inside these walls are cable troughs that hold multiple cables for communications and automatic train control for the Metrorail system.

 

When Metro was not operational in March cables were removed and placed in temporary bypass ductbanks. Temporary bypass ductbanks are a piping system placed underground that secures and protects cables from the surrounding construction. These ductbanks are installed on one side of the track to relocate cables while the new retaining walls are being built. When this process was completed, the existing retaining walls were demolished.

 

Two switches were installed over the course of the Independence Day weekend. These switches will be signaled by Metro's complex train control system to direct trains to the new line or to the existing Orange Line.

 

During Labor Day weekend, double crossover tracks were placed within the existing tracks between Haycock Road and Great Falls Street. Crossovers allow the trains to switch from one set of tracks to another. (See photos.)

 

During the Columbus Day weekend, crews will install the new train control cables that will direct and manage the new line. In 2012, the final step in making the connections between the two lines will be installation of traction power cables to carry power from an existing Metro traction power substation on Fisher Avenue to the tracks. The project is building a train control room near the existing traction power facility as part of the infrastructure needed to support the tie-in.

 

The project is building 11 new traction power substations along the Phase 1 alignment.

 

Construction for Phase 1 is expected to be complete during the Summer of 2013. Once Metro testing is complete, riders will then be able to catch trains from downtown Washington D.C. to Wiehle Avenue in Reston.

 

272.jpg

Crossing Gosnell/Westpark: The cantilevered segmental construction span at the intersection of Route 7 and Gosnell Road continues.

Photo by Stephen Barna, Dulles Corridor Metrorail Project

 

Bridges for Rail Nearing Completion Near Cap One Complex

 

Construction of the aerial bridges for the future Dulles Corridor Metrorail Project tracks along the northwest side of Route 123 in Tysons Corner continues at a rapid pace, using a large, yellow horizontal crane.

 

That crane continues to construct the guideway (bridges) near the future Tysons East Station, at Scotts Crossing Road, and is working over the main entrance to the Capital One campus. This work requires overnight closures of Capital One Drive, between 9:30 p.m. and 5 a.m. and causes those who need access to Capital One in the overnight hours to use Scotts Crossing Road.

 

When those spans are complete, the truss will continue to progress westward, from pier to pier, toward Interstate 495, the Capital Beltway. When the truss completes those segments, it will be disassembled, likely near the end of 2011. That process will takes about four to six weeks.

 

It will then be moved and reassembled in the median of the Dulles International Airport Access Highway/Dulles Toll Road near the Route 7 interchange where it will be used to build the flyover from the Airport/Toll Road median to Route 7 and bridges into the Tysons West Metrorail Station at Spring Hill Road.

 

274.jpg

In The Air: Crews are working to complete portions of the aerial guideway along Route 123 between the Dulles Connector Road and Interstate 495 near the Capital One complex.

Photo by Shea Daugherty, Dulles Transit Partners

 

275.jpg

Along Route 7: This horizontal crane is building bridges in the median of Route 7 working near the Gosnell/Westpark intersection.

Photo by Chuck Samuelson, Dulles Corridor Metrorail Project

 

###

 

Previous construction progress updates in PDF format can be had at the Dulles Corridor Metrorail Project web site.

Link to comment
Share on other sites


Archived

This topic is now archived and is closed to further replies.

×
×
  • Create New...

Important Information

By using this site, you agree to our Terms of Use.