F.png Coney Island-bound trains skip Avenue U and Avenue X [/color]

 

Weekend, 6 AM to 6 PM, Sat and Sun, Jan 12 - 13

 

 

 

What work is causing this G/O?

 

 

 

 

 

On a side note, this means we get views of F trains taking the slip switch from the express to the local track at Avenue X in addition to running express via Culver Viaduct and Bergen Lower during a separate G/O.

 

 

 

I would assume work being done on either Avenue U or X on the CI platform/side.

Link to comment
Share on other sites

  • 1 month later...

  • Replies 3.9k
  • Created
  • Last Reply

2.png Flatbush Av-bound trains run express from 14 St to Chambers St 

 

Late Nights, 12:01 AM to 5:30 AM, every night until further notice. 

 

For Christopher, Houston, Canal and Franklin Sts, take the 1.png instead. 

 

• Transfer between 1.png and 2.png trains at 14 St or Chambers St.

What's going on here? Does it have anything to do with South Ferry?

Link to comment
Share on other sites

I doubt...

 

Southbound (1) service is still normal, why not the (2)...The southbound crossing from local to express is now at 14th instead of Chambers for god who knows, doubling waiting time from 15 to 20 minutes for southbound local customers from 14th to Chambers...

 

I just wonder why this.....

Edited by RollOverMyHead
Link to comment
Share on other sites

I wonder if they're working on the crossover between the downtown tracks north of Chambers. Besides any ridership changes, seems to be a logical answer.

 

On a similar note:

 

 

(2) Wakefield-bound trains skip 79 St and 86 St

Late Nights, 12:15 AM to 5 AM, Tue to Fri, until Mar 22

 

Take the (1) instead.

 

• Transfer between (1) and (2) trains at 72 St or 96 St.

_________________________

 

Only the (2) is affected, wonder why.

Link to comment
Share on other sites

The (2) / (5) do-se-do is back.

 

2.png Flatbush Av-bound trains run local via the 5.png from 149 St-Grand Concourse to Franklin Av
5.png Bowling Green-bound trains run via the 2.png from 149 St-Grand Concourse to Chambers St 

Late Night, 11:30 PM Wed to 5 AM Thu, Feb 27 - 28 

No Flatbush Av-bound service at Park Place, Wall St, Clark St and Hoyt St. 

Flatbush Av-bound 2.png and New Lots Av-bound 4.png trains skip Bergen St, Grand Army Plaza 
and Eastern Pkwy. 

Manhattan-bound 5.png trains run via the 2.png from 149 St-Grand Concourse to Chambers St, 
then make stops at Rector St and Bowling Green. 
Bronx-bound 5.png trains run from Bowling Green to Dyre Av overnight.
Edited by Lance
Link to comment
Share on other sites

Manhattan-bound 5.png trains run via the 2.png from 149 St-Grand Concourse to Chambers St, 

then make stops at Rector St and Bowling Green. 

Bronx-bound 5.png trains run from Bowling Green to Dyre Av overnight.

                    
 hmmm Rector then Bowling Green,"get your south ferry loop pics and vids gentlemen!Two nights only!Get your South Ferry loop pics and vids!"

Edited by Around the Horn
Link to comment
Share on other sites

Gone ahead in time a bit, this service change stood out more than the rest!

 

(2) No trains between 3 Av-149 St and 135th St


shuttle_bus.png Free shuttle buses provide alternate service 
Weekend, 11:30 PM Fri to 5 AM Mon, Mar 22 - 25 

Service operates in two sections: 
  1. Between 241 St and 3 Av-149 St 
  2. Between the 148 St 3.png Station and Flatbush Av 
      
(Trains skip 145 St 3.png in both directions) 

Shuttle buses operate along three routes: 
  1. Between 3 Av-149 St and 135 St 
  2. Between 3 Av-149 St and 149 St-Grand Concourse 
  3. Between 149 St-Grand Concourse and 135 St 

 

Transfer between trains and buses at 3 Av-149 St and 135th St.

 

Only logical reason I can think of for this is work in the 149th St Tunnel,  (2) obviously skips 145 St due to the short platforms there

Link to comment
Share on other sites

Wow, the modernization of the signal system at Roosevelt Av, 71 Av and Union Tpke (the remaining old towers on the line). Is this a replacement with a master tower? I've always wondered about over there. I think I may have hard of such a project, but no one was sure where it would be.

Link to comment
Share on other sites

 

Gone ahead in time a bit, this service change stood out more than the rest!

 

(2) No trains between 3 Av-149 St and 135th St

 

 

shuttle_bus.png Free shuttle buses provide alternate service 

Weekend, 11:30 PM Fri to 5 AM Mon, Mar 22 - 25 

 

Service operates in two sections: 

  1. Between 241 St and 3 Av-149 St 

  2. Between the 148 St 3.png Station and Flatbush Av 

      (Trains skip 145 St 3.png in both directions) 

 

Shuttle buses operate along three routes: 

  1. Between 3 Av-149 St and 135 St 

  2. Between 3 Av-149 St and 149 St-Grand Concourse 

  3. Between 149 St-Grand Concourse and 135 St 

 

Transfer between trains and buses at 3 Av-149 St and 135th St.

 

Only logical reason I can think of for this is work in the 149th St Tunnel,  (2) obviously skips 145 St due to the short platforms there

 

R62 (2) s?

Link to comment
Share on other sites

Gone ahead in time again...

 

(F) Service operates in 2 sections:


1. Between 179 St and Jay St-MetroTech, and via the A.png to/from Hoyt-Schermerhorn 
2. Between Stillwell Av and Bergen St, and via the G.png to/from Bedford-Nostrand Avs 

Late Nights, 11:45 PM to 5 AM, Mon to Thu, Mar 25 - 28 

• Transfer at Hoyt-Schermerhorn to continue your trip.
 
 
Looking at maps, the way the Hoyt-Schermerhorn turn around may work (I think) seems to be to run the train up to Clinton-Washington Aves on the express  (A) track (seeing as that line is local through there at late-night), change ends, run it through a siding between the express tracks between Clinton-Washington Aves and Lafayette Ave and then rejoin the Manhattan-bound (A) express line into Hoyt-Schermerhorn, seems most logical, unless the MTA have other ideas, which given them they might!
Link to comment
Share on other sites

  • 2 weeks later...
  • 1 month later...
  • 2 weeks later...

I wonder what sort of work is going to be done that makes it so that uptown trains can't pass Fulton Street, and downtown trains can't stop there...

 

 

 

 

(A)(C) No service at Fulton St
No transfers between (2)  (3) and (4)  (5) trains at Fulton St 

Weekend, 11:45 PM Fri to 5 AM Mon, Jun 14 - 17 

Brooklyn-bound  (A)  (C) trains skip Fulton St. 

Inwood-bound A.png and 168 St-bound C.png trains run via the F.png from Jay-St MetroTech to W 4 St. 

Travel Alternatives 

For service to Brooklyn, use the nearby Chambers St A.png C.png Station instead. 

For uptown A.png C.png service, take the local 4.png or 5.png* to Bleecker St and transfer 
to the A.png C.png at the F.png platform. 

• Transfer between 2.png 3.png and Brooklyn-bound A.png C.png trains at Chambers St/Park Place. 
• Transfer between 2.png 3.png and uptown A.png C.png trains at Times Sq-42 St/Port Authority. 
• Transfer between 2.png 3.png and 4.png trains at Nevins St. 

*This detour has taken into account additional planned service changes. 

 

Link to comment
Share on other sites

 

I wonder what sort of work is going to be done that makes it so that uptown trains can't pass Fulton Street, and downtown trains can't stop there...

 

 

 

 

(A)(C) No service at Fulton St

No transfers between (2)  (3) and (4)  (5) trains at Fulton St 

Weekend, 11:45 PM Fri to 5 AM Mon, Jun 14 - 17 

 

Brooklyn-bound  (A)  (C) trains skip Fulton St. 

 

Inwood-bound A.png and 168 St-bound C.png trains run via the F.png from Jay-St MetroTech to W 4 St. 

 

Travel Alternatives 

 

For service to Brooklyn, use the nearby Chambers St A.png C.png Station instead. 

 

For uptown A.png C.png service, take the local 4.png or 5.png* to Bleecker St and transfer 

to the A.png C.png at the F.png platform. 

 

• Transfer between 2.png 3.png and Brooklyn-bound A.png C.png trains at Chambers St/Park Place. 

• Transfer between 2.png 3.png and uptown A.png C.png trains at Times Sq-42 St/Port Authority. 

• Transfer between 2.png 3.png and 4.png trains at Nevins St. 

 

*This detour has taken into account additional planned service changes. 

 

Ugh, they did that a while back too, and with the (4)(5). Hate it when they do that.

Link to comment
Share on other sites

Join the conversation

You can post now and register later. If you have an account, sign in now to post with your account.

Guest
Reply to this topic...

×   Pasted as rich text.   Restore formatting

  Only 75 emoji are allowed.

×   Your link has been automatically embedded.   Display as a link instead

×   Your previous content has been restored.   Clear editor

×   You cannot paste images directly. Upload or insert images from URL.

×
×
  • Create New...

Important Information

By using this site, you agree to our Terms of Use.