Union Tpke Posted December 14, 2014 Share #1 Posted December 14, 2014 MTA says its now forecasting the opening day is: 2nd Quarter of 2015 instead of February 2015. ( All parties are working together to bring the construction completion as close as possible to the original agreed upon date.) MTA's Independent Engineer is reporting on April Fools day 2015. Main reasons... 1. Fire Alarm systems... problems with the test. Major hold up, they can not test : Escalators, Elevators, CCTV, Ventilation fans etc. 2. Inclined Elevators.... Fail two times at the factory test. There is a delay of testing and installing at the station. 3. Testing & Acceptance of Transmission Backbone System... due to test delay submission. MTA's Independent Engineer report also finds... • Two systems, fire alarm and backbone communications remain on the critical path of the Systems and Finishes contractor’s schedule and continue to be delayed. • Several systems (fire alarm, radio systems, computer based dispatch, train ID) have not reached the appropriate test level to start operator Training and continue to be delayed. • Additional mitigations have been proposed, including the prioritization of contractor acceptance testing and NYCT review/approval cycles. MTACC has obtained additional testing & commissioning experts with NYCT expertise to further advance the schedule. • NYCT continues to provide the requested support for the compressed schedule, but significant schedule risk remains as there is no contingency on multiple system paths. • As a result, the IEC forecasts a revenue service date no earlier than April 2015. Note: No problems on the escalators and entire project budget remains on track ($9 million under budget) Link to comment Share on other sites More sharing options...
Javier Posted December 14, 2014 Share #2 Posted December 14, 2014 ARE YOU KIDDING ME!?!?!?!?!?!? Link to comment Share on other sites More sharing options...
Q43LTD Posted December 14, 2014 Share #3 Posted December 14, 2014 It's just like the new South Ferry station all over again Link to comment Share on other sites More sharing options...
MysteriousBtrain Posted December 14, 2014 Share #4 Posted December 14, 2014 Why am I not suprised? Link to comment Share on other sites More sharing options...
bobtehpanda Posted December 14, 2014 Share #5 Posted December 14, 2014 Is there an actual source? Link to comment Share on other sites More sharing options...
alekr Posted December 14, 2014 Share #6 Posted December 14, 2014 April Fools day 2015. Look carefully! Link to comment Share on other sites More sharing options...
MysteriousBtrain Posted December 14, 2014 Share #7 Posted December 14, 2014 April Fools day 2015. Look carefully! Wow.... It's too early for that lol. Link to comment Share on other sites More sharing options...
NYtransit Posted December 14, 2014 Share #8 Posted December 14, 2014 i feel like the workers when they build something they dont know what their doing till the last minute...OR they are just looking for overtime pay. Link to comment Share on other sites More sharing options...
Javier Posted December 14, 2014 Share #9 Posted December 14, 2014 This is just unbelivable! So now because of this I think that the SAS will be completed in 2031. I doubt we will see this finished until after next summer. Link to comment Share on other sites More sharing options...
Lance Posted December 14, 2014 Share #10 Posted December 14, 2014 The race is on folks. Which station will (re-)open first, Cortlandt St , South Ferry , or 34 St-Javits Center ? Link to comment Share on other sites More sharing options...
Xfer2Nowhere Posted December 14, 2014 Share #11 Posted December 14, 2014 It's too bad this had to happen again, but it's expected. That's how construction rolls around here. I was waiting to take this to the Auto Show this year instead of the M34+, but I have a feeling they'll miss that deadline too. Link to comment Share on other sites More sharing options...
justhafacts Posted December 15, 2014 Share #12 Posted December 15, 2014 at this rate the extension will open first Link to comment Share on other sites More sharing options...
Javier Posted December 15, 2014 Share #13 Posted December 15, 2014 The race is on folks. Which station will (re-)open first, Cortlandt St , South Ferry , or 34 St-Javits Center ? I don't think 34 Street qualifies as a "reopen" station Lance. Link to comment Share on other sites More sharing options...
MysteriousBtrain Posted December 15, 2014 Share #14 Posted December 15, 2014 Hold on a second. At bobtehpanda asked, is there a reliable source for the Extension delay because 1. It seems fishy it will be delayed to April Fools day and 2. I tried to find a source myself and nothing came up on google. I don't think 34 Street qualifies as a "reopen" station Lance. Lance means which of the 3 stations would be in passenger service first. Link to comment Share on other sites More sharing options...
CenSin Posted December 15, 2014 Share #15 Posted December 15, 2014 I don't think 34 Street qualifies as a "reopen" station Lance. Hence the parentheses around re. Link to comment Share on other sites More sharing options...
Grand Concourse Posted December 15, 2014 Share #16 Posted December 15, 2014 Wth does the station need an inclined elevator? Link to comment Share on other sites More sharing options...
AndrewJC Posted December 15, 2014 Share #17 Posted December 15, 2014 Hold on a second. At bobtehpanda asked, is there a reliable source for the Extension delay because 1. It seems fishy it will be delayed to April Fools day and 2. I tried to find a source myself and nothing came up on google. http://web.mta.info/mta/news/books/pdf/141215_1345_CPOC.pdf - pages 31 and 42 both give April 1 as the earliest likely opening date. Wth does the station need an inclined elevator? It needs an elevator of some sort because of ADA. An inclined elevator can share the escalator shaft. A standard vertical elevator requires dedicated vertical and horizontal shafts. Presumably, when the plans were being developed, the inclined option was the cheaper of the two. (Whether it worked out that way in the end I have no idea.) Link to comment Share on other sites More sharing options...
Grand Concourse Posted December 15, 2014 Share #18 Posted December 15, 2014 Oh I understand the need for an elevator because the ada laws mandate all new stations be built with one, but i'm still trying to picture why they need to be inclined for this station. Link to comment Share on other sites More sharing options...
MysteriousBtrain Posted December 15, 2014 Share #19 Posted December 15, 2014 Thank you Andrew. Anyways, If the keeps postponing the Extension opening date, people will be upset and would have to force the station to be a bellmouth. Given the completion of the extension, it is too late for it to become a bellmouth. Link to comment Share on other sites More sharing options...
CenSin Posted December 15, 2014 Share #20 Posted December 15, 2014 Oh I understand the need for an elevator because the ada laws mandate all new stations be built with one, but i'm still trying to picture why they need to be inclined for this station.Already answered by the post you're replying to: An inclined elevator can share the escalator shaft. A standard vertical elevator requires dedicated vertical and horizontal shafts. Presumably, when the plans were being developed, the inclined option was the cheaper of the two. (Whether it worked out that way in the end I have no idea.)The idea is to drill once instead of twice. Link to comment Share on other sites More sharing options...
Grand Concourse Posted December 15, 2014 Share #21 Posted December 15, 2014 Very well then. Might be more interesting than the subway ride if it is an inclined rail type car. Link to comment Share on other sites More sharing options...
pjbr40 Posted December 15, 2014 Share #22 Posted December 15, 2014 Is this becoming a Second Ave Subway Junior ? ( when they city was trying to get second ave subwayand can never get it open after all these years) Link to comment Share on other sites More sharing options...
CenSin Posted December 15, 2014 Share #23 Posted December 15, 2014 They have the tunnels, tracks, and signals in order. I highly doubt that even if there were minor problems, politicians would let the opening delay further. It's so tantalizingly close to completion that I wouldn't be surprised if they just opened it anyway and left the non-essentials (which I consider to include ADA-accessibility) to ongoing work after opening. The station cavern is huge and they have plenty of space to continue this work while the station is in service. Link to comment Share on other sites More sharing options...
Union Tpke Posted December 15, 2014 Author Share #24 Posted December 15, 2014 http://www.nydailynews.com/new-york/opening-no-7-subway-extension-delayed-spring-article-1.2046161 Link to comment Share on other sites More sharing options...
Fresh Pond Posted December 15, 2014 Share #25 Posted December 15, 2014 They have the tunnels, tracks, and signals in order. I highly doubt that even if there were minor problems, politicians would let the opening delay further. It's so tantalizingly close to completion that I wouldn't be surprised if they just opened it anyway and left the non-essentials (which I consider to include ADA-accessibility) to ongoing work after opening. The station cavern is huge and they have plenty of space to continue this work while the station is in service. ADA laws mandate otherwise. Station has to be open with FULL accessibility or face a lawsuit Link to comment Share on other sites More sharing options...
Recommended Posts
Archived
This topic is now archived and is closed to further replies.