M.T.A. Construction Costs ‘Threaten to Strangle’ Growth, Report Warns


GojiMet86

Recommended Posts

https://www.nytimes.com/2018/02/05/nyregion/mta-construction-costs-threaten-to-strangle-growth-report-warns.html

Quote

 

M.T.A. Construction Costs ‘Threaten to Strangle’ Growth, Report Warns

By BRIAN M. ROSENTHALFEB. 5, 2018

 

The Metropolitan Transportation Authority could dramatically reduce its sky-high construction costs by rethinking how it manages projects, prioritizing efficiency over bureaucracy and ending rules that require far more workers than are needed, according to a new report based on two years of research.

The report, scheduled to be published on Tuesday by the Regional Plan Association, an urban research and advocacy group, says that dozens of missteps, abuses and inefficiencies have helped to make New York City the most expensive place in the world for public transit projects.

Among other factors, the report’s authors found that recent megaprojects like the first phase of the Second Avenue Subway on Manhattan’s Upper East Side have suffered from overly burdensome environmental reviews, repeated political interference, out-of-date work rules, “excessive customization” and a lack of coordination, communication and accountability.

“The extraordinarily high costs are due to many factors at every stage, from decisions by political leaders at the inception of a project to the final stages of a lengthy process of planning, design, and construction,” wrote the authors, Richard Barone, Julia Vitullo-Martin and Alyssa Pichardo. “Long tolerated as an accepted natural consequence of New York’s size and dominance, these costs threaten to strangle New York’s future economic growth.”

In addition to the Second Avenue Subway, the report examines the extension of the No. 7 Line to the Far West Side of Manhattan and East Side Access, a project, still underway, to link the Long Island Rail Road to Grand Central Terminal through a 3½-mile-long tunnel. The report compares the projects with similarly ambitious transit projects in London, Paris and Los Angeles.

The report largely echoes the findings of an investigation published by The New York Times in December. That investigation found that a mile of train track in New York cost at least five times as much as anywhere else in the world, an inefficient use of money that had sapped funding that could have been used to fix the aging subway system. It blamed public officials who stood by as a small group of politically connected labor unions, construction companies and consulting firms amassed large profits.

The Regional Plan Association report goes a step further by recommending 11 different measures to rein in costs.

The transportation authority should create a separate management agency to run each megaproject, according to the report, which cites a similar model that is used in London. Officials also should streamline the environmental review process, expand the use of design-build contracting rather than have separate contracts for each, and allow the use of private workers for more tasks, the authors recommend. Work rules should be changed to reduce unnecessary staffing and overtime, they say.

The report also notes a variety of ways that other transit systems achieve efficiencies, including private-public partnerships, innovative insurance policies, and performance bonuses for workers and contractors.

Together, the changes could cut construction costs by a third, the group said.

In response to a request for comment, an M.T.A. spokesman, Jon Weinstein, said in an email: “Tackling outsized capital costs is a key goal of the M.T.A.’s new leadership team. Chairman Lhota created a board task force to specifically and aggressively attack this problem. Among other things, as part of this initiative M.T.A. leadership is working to streamline the procurement process, stop customization of components, reduce change orders, chop huge costs and delays associated with utility relocations, and more effectively manage projects across the board. We look forward to reviewing the report.” The authority’s chairman is Joseph J. Lhota.

The report is likely to spur discussion at a time when state lawmakers are debating how to address the failing subway system. Only about 65 percent of trains now reach their destination on time, the lowest level in decades and the lowest of any major rapid transit system in the world.

Gov. Andrew M. Cuomo, a second-term Democrat who controls the M.T.A., which operates the subway and the region’s buses and commuter railroads, has proposed a congestion pricing system for vehicles entering Manhattan’s most crowded neighborhoods to increase funding for public transit. But some critics have resisted, saying the authority should prove it can wisely spend money before getting more.

Councilwoman Helen Rosenthal, Democrat of Manhattan, called the report’s proposals “a great start.” In particular, Ms. Rosenthal, who last fall led a group of council members who sent a letter to the authority demanding an independent commission to study the costs, praised the idea of the special management agencies for each project.

“The M.T.A.’s sky-high costs aren’t some immutable fact of nature; they’re the result of flawed processes and outdated practices,” she said. “What’s been desperately needed has been a willingness to shake up those practices, to bring in new competition and innovation, and to make the M.T.A. accountable to the public.”

 

 

Link to comment
Share on other sites


 Is the MTA allowed to outsource labor? If the union refuses to get rid of their useless jobs, excessive workers, and senseless fees, the MTA should have the right to go and outsource to non-union labor if they can build it quicker and for less. It's crazy you need to have 10 people working on one rail during a service change when you need only a few.

Link to comment
Share on other sites

5 minutes ago, R68OnBroadway said:

 Is the MTA allowed to outsource labor? If the union refuses to get rid of their useless jobs, excessive workers, and senseless fees, the MTA should have the right to go and outsource to non-union labor if they can build it quicker and for less. It's crazy you need to have 10 people working on one rail during a service change when you need only a few.

Ha, yeah right!  

Link to comment
Share on other sites

1 hour ago, R68OnBroadway said:

 Is the MTA allowed to outsource labor? If the union refuses to get rid of their useless jobs, excessive workers, and senseless fees, the MTA should have the right to go and outsource to non-union labor if they can build it quicker and for less. It's crazy you need to have 10 people working on one rail during a service change when you need only a few.

There's no law saying (MTA) has to use union labor. It's all politics that makes union labor the norm.

And even still, Parsons and Skanska will subcontract out work to Union forms before non-union firms.

 

 

Link to comment
Share on other sites

15 hours ago, Deucey said:

There's no law saying (MTA) has to use union labor. It's all politics that makes union labor the norm.

And even still, Parsons and Skanska will subcontract out work to Union forms before non-union firms.

 

 

Skanska is one of the big boys in the industry. I came close to working for them in fact, but they have a hold on the really big projects, that's for sure.  In the construction industry, it's hard to break up habits if you will.  The same GCs use the same subs, and the same subs use the same subs and so on.  

Link to comment
Share on other sites

16 hours ago, R68OnBroadway said:

 Is the MTA allowed to outsource labor? If the union refuses to get rid of their useless jobs, excessive workers, and senseless fees, the MTA should have the right to go and outsource to non-union labor if they can build it quicker and for less. It's crazy you need to have 10 people working on one rail during a service change when you need only a few.

The distinction to make here (and part of the reason why this is such a major problem) is that the MTA does not have in-house workers for major capital construction projects, so they're not the ones negotiating labor agreements, the contractors are. As long as the unions and management get their cut and any wise politicians get a wonderful steak dinner or mysteriously primaried in the next election, there's no incentive for anyone to actually cut costs.

Link to comment
Share on other sites

On 2/6/2018 at 11:36 AM, Via Garibaldi 8 said:

Nothing new here... The only question is when will we see real changes.  If the union has any say, they won't have any part in fewer workers being at these sites and they'll say that their salaries aren't enough for what they endure.

Pretty much this, its depressing but they really do have far too much power. If we want to see change in the way projects are handled the unions will need to be throttled. Some politician (think its the republican candidate for governor) once said something along the lines of "unions are mining gold in the tunnels of NYC and nobody is batting an eye," which is absolutely true. Pic related always springs to mind

yptH0xn.jpg 

[img=https://i.imgur.com/yptH0xn.jpg]
<blockquote class="imgur-embed-pub" lang="en" data-id="yptH0xn"><a href="//imgur.com/yptH0xn">View post on imgur.com</a></blockquote><script async src="//s.imgur.com/min/embed.js" charset="utf-8"></script>

(really hope one of these works I no idea how to inset images into a post)

 

19 hours ago, R68OnBroadway said:

Is the MTA allowed to outsource labor? If the union refuses to get rid of their useless jobs, excessive workers, and senseless fees, the MTA should have the right to go and outsource to non-union labor if they can build it quicker and for less. It's crazy you need to have 10 people working on one rail during a service change when you need only a few.

My understanding is that while its not technically illegal or anything It will cause a massive union boycott of the MTA, in addition being blocked by politicians who are payed to lobby for union interests,

Link to comment
Share on other sites

6 minutes ago, kosciusko said:

Pretty much this, its depressing but they really do have far too much power. If we want to see change in the way projects are handled the unions will need to be throttled. Some politician (think its the republican candidate for governor) once said something along the lines of "unions are mining gold in the tunnels of NYC and nobody is batting an eye," which is absolutely true. Pic related always springs to mind

yptH0xn.jpg 


[img=https://i.imgur.com/yptH0xn.jpg]

<blockquote class="imgur-embed-pub" lang="en" data-id="yptH0xn"><a href="//imgur.com/yptH0xn">View post on imgur.com</a></blockquote><script async src="//s.imgur.com/min/embed.js" charset="utf-8"></script>

(really hope one of these works I no idea how to inset images into a post)

 

My understanding is that while its not technically illegal or anything It will cause a massive union boycott of the MTA, in addition being blocked by politicians who are payed to lobby for union interests,

I see the same crap when I take Metro-North.   About EIGHT guys on the tracks, one talking and one actually doing something.  The other six act as if it's their first day on the job.  It's absurd that the union can even try to defend such a waste of resources. If there was a safety issue, those six guys standing doing nothing would be of no help.

Link to comment