Union Tpke Posted July 26, 2019 Share #1 Posted July 26, 2019 (edited) Project: T7040402 Description: Procurement of Low Turnstile Automated Fare Control Category: Passenger Stations Element: Fare Collection xxxxxxxxxx ... This project will purchase low turnstiles and end cabinets to support improvements at fare control areas at various stations throughout the system. http://web.mta.info/capitaldashboard/allframenew_pi.php?PROJNUM=t7040402&PLTYPE=5&DISPLAYALL=N http://web.mta.info/capitaldashboard/allframenew_budget.php?PROJNUM=t7040402&PLTYPE=5 http://web.mta.info/capitaldashboard/allframenew_budhist.php?PROJNUM=t7040402&PLTYPE=5 Doubling of scope from 176 turnstiles to 352 turnstiles resulted in change of completion date. CHAOS! New York City Transit Project: T7040716 Description: Replace 1 Elevator at Lexington Av-53 St Station on the Queens Boulevard Line - Design Only Category: Passenger Stations Element: Station Escalators / Elevators xxxxxxxxxx ... This project will provide design funding to replace one hydraulic elevator at Lexington Av-53 St Station on the Queens Boulevard Line. Construction will be addressed in a future capital program. http://web.mta.info/capitaldashboard/allframenew_pi.php?PROJNUM=t7040716&PLTYPE=1&DISPLAYALL=N http://web.mta.info/capitaldashboard/allframenew_budget.php?PROJNUM=t7040716&PLTYPE=1 http://web.mta.info/capitaldashboard/allframenew_budhist.php?PROJNUM=t7040716&PLTYPE=1 New York City Transit Project: T7040715 Description: Replace 11 Elevators at 5 Stations - Design Only Category: Passenger Stations Element: Station Escalators / Elevators xxxxxxxxxx ... This project will provide design funding to replace 11 hydraulic elevators at 5 stations in Manhattan and Brooklyn. Locations include: 2 at 34 St and 2 at 72 St on the Broadway-7 Ave Line in Manhattan; and 3 at Pacific St on the 4 Ave Line, 2 at Atlantic Ave on the Eastern Parkway Line, and 2 at Atlantic Ave on the Brighton Line in Brooklyn. Construction will be addressed in a future capital program. http://web.mta.info/capitaldashboard/allframenew_pi.php?PROJNUM=t7040715&PLTYPE=1&DISPLAYALL=N http://web.mta.info/capitaldashboard/allframenew_budget.php?PROJNUM=t7040715&PLTYPE=1 http://web.mta.info/capitaldashboard/allframenew_budhist.php?PROJNUM=t7040715&PLTYPE=1 New York City Transit Project: T7040718 Description: Replace 11 Escalators at 6 Stations - Design Only Category: Passenger Stations Element: Station Escalators / Elevators xxxxxxxxxx ... This project will provide design funding to replace 11 escalators at 6 stations in Manhattan and the Bronx. Locations include: 2 at 59 St on the Lexington Ave Line, 2 at 7 Ave-53 St and 2 at 5 Ave on the Queens Boulevard Line, 2 at West 4 St on the 8 Ave Line and 2 at Delancy on the 6 Ave Line in Manhattan; and 1 at 161 St- Yankee Stadium on the Concourse Line in the Bronx. Construction will be addressed in a future capital program. http://web.mta.info/capitaldashboard/allframenew_pi.php?PROJNUM=t7040718&PLTYPE=1&DISPLAYALL=N http://web.mta.info/capitaldashboard/allframenew_budget.php?PROJNUM=t7040718&PLTYPE=1 http://web.mta.info/capitaldashboard/allframenew_budhist.php?PROJNUM=t7040718&PLTYPE=1 New York City Transit Project: T7040717 Description: Replace 6 Escalators at 4 Stations - Design Only Category: Passenger Stations Element: Station Escalators / Elevators xxxxxxxxxx ... This project will provide design funding to replace 6 escalators at 4 stations in Manhattan and Queens. Locations include: 2 at 59 St on the Lexington Ave Line, 1 at 59 St on the Broadway Line, and 2 at 5 Ave on the Queens Boulevard Line in Manhattan; and 1 at 74 St on the Flushing Line in Queens. Construction will be addressed in a future capital program. http://web.mta.info/capitaldashboard/allframenew_pi.php?PROJNUM=t7040717&PLTYPE=1&DISPLAYALL=N http://web.mta.info/capitaldashboard/allframenew_budget.php?PROJNUM=t7040717&PLTYPE=1 New York City Transit Project: T7070321 Description: Priority Structural Repairs on the 4th Avenue Line - Phase 2 Category: Line Structures Element: Line Structure Rehabilitation xxxxxxxxxx ... This project is the second phase of the rehabilitation of subway structure of the 4th Avenue Line between 59 Street and 36 Street stations, located in the borough of Brooklyn. This project will focus on high priority structural component repair work. Work will include sealing water leaks and leaking cracks in walls, ceilings & ventilators; repairing spalled concrete; repairing ventilator structures and emergency exits; replacing corroded steel members; and repairing a deteriorated duct bench. Construction End March 2020 Budget increase is due to critical structural defects uncovered during construction and a time constrained service plan that shifted production to a 24-7 operation. Additional funding was needed for construction contingency, consultant support and in-house services. http://web.mta.info/capitaldashboard/allframenew_pi.php?PROJNUM=t7070321&PLTYPE=1&DISPLAYALL=N http://web.mta.info/capitaldashboard/allframenew_budhist.php?PROJNUM=t7070321&PLTYPE=1 Moved from 34th to 28th to 27th New York City Transit Project: T7090220 Description: New Substation at 27 Street on the 8 Avenue Line Category: Traction Power Element: Substations xxxxxxxxxx ... This project will construct a new substation serving the IND 8 Avenue Line in the vicinity of 27 Street and 8 Avenue in order to provide traction power for reliable train operations on the 8 Avenue Line. http://web.mta.info/capitaldashboard/allframenew_pi.php?PROJNUM=t7090220&PLTYPE=1&DISPLAYALL=N http://web.mta.info/capitaldashboard/allframenew_budhist.php?PROJNUM=t7090220&PLTYPE=1 New York City Transit Project: T7160737 Description: Fare Evasion Cameras Category: Misc./Emergency Element: Employee Facilities xxxxxxxxxx ... This project will provide for fare evasion monitors and fare evasion CCTV cameras at designated stations. Schedule dates are not available, due to project being under development. http://web.mta.info/capitaldashboard/allframenew_pi.php?PROJNUM=t7160737&PLTYPE=5&DISPLAYALL=N http://web.mta.info/capitaldashboard/allframenew_budhist.php?PROJNUM=t7160737&PLTYPE=5 Project: T7041417 Description: Planning & Engineering Study at Sutphin Blvd-Archer Av Category: Passenger Stations Element: Other Station Improvements xxxxxxxxxx ... The project will undertake a feasibility study and other planning and design efforts for improvement of the interconnection between the Sutphin Boulevard/Archer Avenue/JFK Airport subway station, located on the Archer Avenue line in Queens, and the adjacent LIRR Jamaica Station and JFK AirTrain facilities. Improvements to be considered include the addition of elevator/escalator vertical circulation capacity, replacement/upgrade of some station finishes, and system enhancements. Schedule dates are not available, due to project being under development. New York City Transit Project: T7041422 Description: Station Circulation Enhancements at Main St on the Flushing Line Category: Passenger Stations Element: Other Station Improvements xxxxxxxxxx ... This project will fund design activities to provide circulation enhancements at platform and street stairs at Main St station on the Flushing Line in Queens. Some schedule dates are not available, due to project being under development. http://web.mta.info/capitaldashboard/allframenew_pi.php?PROJNUM=t7041422&PLTYPE=1&DISPLAYALL=N New York City Transit Project: T7041415 Description: Station Capacity Enhancements at Myrtle Avenue on the Jamaica Line Category: Passenger Stations Element: Other Station Improvements xxxxxxxxxx ... This project will provide a new station entrance at the Myrtle Avenue Station on the Jamaica Line in Brooklyn. The scope of work includes street stairs, a mezzanine extension, and a service area. Some schedule dates are not available, due to project being under development. http://web.mta.info/capitaldashboard/allframenew_pi.php?PROJNUM=t7041415&PLTYPE=1&DISPLAYALL=N Edited July 27, 2019 by Union Tpke i wasn't done 0 Quote Link to comment Share on other sites More sharing options...
LGA Link N Train Posted July 27, 2019 Share #2 Posted July 27, 2019 That’s good. I read some of these improvements a few days ago. It’s good that they’re looking to Improve Myrtle, Sutphin/Archer and Main Street. Those Stations do get crowded at times and with the current layout, it doesn’t really help that much. 0 Quote Link to comment Share on other sites More sharing options...
Union Tpke Posted July 28, 2019 Author Share #3 Posted July 28, 2019 New York City Transit Project: T7100441 Description: New Railcar Receiving Facility Category: Shops And Yards Element: Shops And Yards xxxxxxxxxx ... This project will construct improved facilities for the intake and testing of new railcars in preparation for the high volume of railcars to be delivered in coming years. Construction Start Apr 2020 End Jun 2022 http://web.mta.info/capitaldashboard/allframenew_pi.php?PROJNUM=t7100441&PLTYPE=1&DISPLAYALL=N http://web.mta.info/capitaldashboard/allframenew_budhist.php?PROJNUM=t7100441&PLTYPE=1 0 Quote Link to comment Share on other sites More sharing options...
Union Tpke Posted July 28, 2019 Author Share #4 Posted July 28, 2019 Project: T7080323 Description: Modification of Signal Key-By Circuits - Phase 4 Category: Signals & Communications Element: Signal Modernization xxxxxxxxxx ... This project will upgrade signal locations systemwide by incorporating a signal key-by timer into the existing circuits of automatic and approach signals at the leaving end of station platforms. In-house staff was diverted to Subway Action Plan (SAP) work - anticipate to restart work for completion by 2021. http://web.mta.info/capitaldashboard/allframenew_pi.php?PROJNUM=t7080323&PLTYPE=5&DISPLAYALL=N http://web.mta.info/capitaldashboard/allframenew_budhist.php?PROJNUM=t7080323&PLTYPE=5 0 Quote Link to comment Share on other sites More sharing options...
CenSin Posted July 28, 2019 Share #5 Posted July 28, 2019 On 7/26/2019 at 7:43 PM, Union Tpke said: New York City Transit Project: T7041422 Description: Station Circulation Enhancements at Main St on the Flushing Line Category: Passenger Stations Element: Other Station Improvements xxxxxxxxxx ... This project will fund design activities to provide circulation enhancements at platform and street stairs at Main St station on the Flushing Line in Queens. Some schedule dates are not available, due to project being under development. http://web.mta.info/capitaldashboard/allframenew_pi.php?PROJNUM=t7041422&PLTYPE=1&DISPLAYALL=N Having used that station for so many years, it’s about time they did something to improve circulation. All the street entrances are clogged with people going in and out. They need some exits closer to the Skyview Center area. 0 Quote Link to comment Share on other sites More sharing options...
bobtehpanda Posted July 31, 2019 Share #6 Posted July 31, 2019 On 7/28/2019 at 5:06 AM, CenSin said: Having used that station for so many years, it’s about time they did something to improve circulation. All the street entrances are clogged with people going in and out. They need some exits closer to the Skyview Center area. The biggest changer would be to have a subway entrance at the Library. There are lots of folks walking from bus stops over there as it is. Put in some retail space and you'd probably make tons of money. 0 Quote Link to comment Share on other sites More sharing options...