Kingsbridgeviewer382 Posted April 19 Share #76 Posted April 19 15 minutes ago, Chris89292 said: UPDATE: Flushing bound platforms will be closed on May 6th until Q1 2025 😒 Crazy……. should be done in 6 months not another 11 month delay Pretty sure you and many others would have complained if this was a rush job instead. 1 Quote Link to comment Share on other sites More sharing options...
Chris89292 Posted April 19 Author Share #77 Posted April 19 (edited) 14 minutes ago, Kingsbridgeviewer382 said: Pretty sure you and many others would have complained if this was a rush job instead. The community has the right to complain, the MTA doesn’t promise anything on time anyway, all their recent projects have been delayed for months, especially for the stations in Jamaica. A 6-7 month construction project is enough time, I would accept a month of delay or 2 Edited April 19 by Chris89292 0 Quote Link to comment Share on other sites More sharing options...
slantfan4281 Posted April 20 Share #78 Posted April 20 3 hours ago, Chris89292 said: UPDATE: Flushing bound platforms will be closed on May 6th until Q1 2025 😒 Crazy……. should be done in 6 months not another 11 month delay What's the schedule for the rest of the stops, has it changed 0 Quote Link to comment Share on other sites More sharing options...
Chris89292 Posted April 20 Author Share #79 Posted April 20 5 hours ago, slantfan4281 said: What's the schedule for the rest of the stops, has it changed The only information right now is that 69th and 52nd street will close anytime in 2024, and 103 Street will close in 2025 1 Quote Link to comment Share on other sites More sharing options...
Wallyhorse Posted April 22 Share #80 Posted April 22 I suspect a lot of this is not having enough workers for such. Many people retired during the pandemic and will continue to take some time for all those positions to be filled again. 1 Quote Link to comment Share on other sites More sharing options...
Chris89292 Posted April 27 Author Share #81 Posted April 27 (edited) I think the cause of the delays was because of the queensboro plaza elevator project that shut down the line in half for 3 weeks, which disrupt track access at 82nd and 111 street, all of this happening in January and February is what causes the project to get delayed to April rather then it’s original opening date in March Edited April 27 by Chris89292 0 Quote Link to comment Share on other sites More sharing options...
Chris89292 Posted May 3 Author Share #82 Posted May 3 Today is officially the last day of Flushing bound service at 111 and 82nd Street, 11:45 PM Also a quick update at Woodside 61st street, the contractors are installing new steel beams where the express tracks are since the old ones have been in such corroded conditions, I’m pretty sure this is the reason why the project is so delayed, it also explains the big huge yellow machines on both ends of the station 0 Quote Link to comment Share on other sites More sharing options...
Chris89292 Posted May 4 Author Share #83 Posted May 4 It seems like 69th and 52nd street will be seeing overcoat painting beneath the platforms “I’m referring to the steel beams” there is strange yellow wood planks beneath the train tracks, and there is some construction noise around that area. Also at Queensboro Plaza, the first LED ads are being installed 0 Quote Link to comment Share on other sites More sharing options...
Ale188 Posted May 4 Share #84 Posted May 4 they should honestly should add some safety features like PFSD and such to these revamped stations 0 Quote Link to comment Share on other sites More sharing options...
Chris89292 Posted May 6 Author Share #85 Posted May 6 So it seems like the contractors are finally doing this fast, at least at 111 Street the signs and benches everything has been removed, I also want to point out that they are now doing all this without the blue walls that they used last year, it’s now just gated at both stations, 82nd street has a few exposed areas, hopefully this way the project will be faster. If everything goes fine, we could potentially see the windscreens/walls gone by this month. 0 Quote Link to comment Share on other sites More sharing options...
Chris89292 Posted May 7 Author Share #86 Posted May 7 Here’s is a link to a Skanska safety week video, showcasing the work that’s happening at Woodside 61 Street, there is a few scenes of what’s hidden the blue walls The platforms have been removed on both platforms in half, the the steel beam structures are being repaired and replaced, this is the reason for why the project is delayed 1 Quote Link to comment Share on other sites More sharing options...
darkstar8983 Posted May 7 Share #87 Posted May 7 44 minutes ago, Chris89292 said: Here’s is a link to a Skanska safety week video, showcasing the work that’s happening at Woodside 61 Street, there is a few scenes of what’s hidden the blue walls The platforms have been removed on both platforms in half, the the steel beam structures are being repaired and replaced, this is the reason for why the project is delayed I’m assuming that at some point, this type of work will shift to the local tracks, leaving one-way express service and one-way local service between 74 St-Broadway and Queensboro Plaza, likely concurrent with the 69 St and 52 St work. And I’m assuming also temporary platforms will be set up at 46 St and 33 St (40 St too, or likely skipped) 0 Quote Link to comment Share on other sites More sharing options...
Chris89292 Posted May 9 Author Share #88 Posted May 9 Update at Queensboro plaza: The elevator structure has been installed outside the south end of the station, by the way, the plan is to rebuild the ramp that leads to the station, so they’ll most likely replace the old staircase. 111 Street: The contractors have removed the stair railings, not the whole staircase just the railings, and they’ve removed the fence the leads to an abandoned staircase at the east end of the station, this most likely means the Windscreens/walls will be removed by next week. 0 Quote Link to comment Share on other sites More sharing options...
Kingsbridgeviewer382 Posted May 10 Share #89 Posted May 10 On 5/6/2024 at 11:05 PM, darkstar8983 said: I’m assuming that at some point, this type of work will shift to the local tracks, leaving one-way express service and one-way local service between 74 St-Broadway and Queensboro Plaza, likely concurrent with the 69 St and 52 St work. And I’m assuming also temporary platforms will be set up at 46 St and 33 St (40 St too, or likely skipped) As of now, those stations will be skipped when either manhattan or queens bound platforms are closed. Makes sense to have the unused track open for construction trains to run along. 0 Quote Link to comment Share on other sites More sharing options...
IAlam Posted May 12 Share #90 Posted May 12 On 5/6/2024 at 10:18 PM, Chris89292 said: Here’s is a link to a Skanska safety week video, showcasing the work that’s happening at Woodside 61 Street, there is a few scenes of what’s hidden the blue walls {VIDEO} The platforms have been removed on both platforms in half, the the steel beam structures are being repaired and replaced, this is the reason for why the project is delayed so around 2:13 they show what appears to be a pair of escalators does anywhere know where that is? 0 Quote Link to comment Share on other sites More sharing options...
Chris89292 Posted May 12 Author Share #91 Posted May 12 13 hours ago, IAlam said: so around 2:13 they show what appears to be a pair of escalators does anywhere know where that is? That’s at 74th street, Skanska is also replacing and repairing escalators at that station as part of the project 1 Quote Link to comment Share on other sites More sharing options...
IAlam Posted May 12 Share #92 Posted May 12 4 hours ago, Chris89292 said: That’s at 74th street, Skanska is also replacing and repairing escalators at that station as part of the project If there's one project that feels like it's taking forever it's that one. 0 Quote Link to comment Share on other sites More sharing options...
Chris89292 Posted May 20 Author Share #93 Posted May 20 The walls have been added at 111 Street, with the top area exposed to see through, and a new staircase has been built at 111 Street not open. Also the new walls have been installed at the west end of the station, only a small portion has been built, nothing much to see today at both stations 0 Quote Link to comment Share on other sites More sharing options...
Chris89292 Posted May 20 Author Share #94 Posted May 20 At 82nd street the roof is being taken down, as well as the fences outside the station, only half of the windscreens have been removed, again nothing much at all to see here 0 Quote Link to comment Share on other sites More sharing options...
Chris89292 Posted May 20 Author Share #95 Posted May 20 Today I went to grand central and wow they have closed off 2 stairs that go to the , of course this was meant to happen to expand the area as seen on the renderings posted up at the station, it’ll be so crowded during rush hours, at least the escalators have reopened, I’ll check on the escalators at 74th street as soon as possible 0 Quote Link to comment Share on other sites More sharing options...
7-express Posted May 21 Share #96 Posted May 21 4 hours ago, Chris89292 said: Today I went to grand central and wow they have closed off 2 stairs that go to the , of course this was meant to happen to expand the area as seen on the renderings posted up at the station, it’ll be so crowded during rush hours, at least the escalators have reopened, I’ll check on the escalators at 74th street as soon as possible Aren't they installing platform barriers there too? I saw markings along the platform that appeared to be for it. 0 Quote Link to comment Share on other sites More sharing options...
Chris89292 Posted May 21 Author Share #97 Posted May 21 4 hours ago, 7-express said: Aren't they installing platform barriers there too? I saw markings along the platform that appeared to be for it. Yeah but with all the work being done at 82nd street and 111 Street the MTA has no time to create a GO for Queensboro Plaza-Main Street service, unless they do the work at midnight 0 Quote Link to comment Share on other sites More sharing options...
IAlam Posted May 25 Share #98 Posted May 25 I haven't seen this elsewhere but on some of the R188's, I noticed they've taken the overhead displays on the inside of the car and pulled them back so that they could add a small camera. I guess that's their budget-friendly way of retrofitting trains with cameras. 0 Quote Link to comment Share on other sites More sharing options...
T J Trainman Posted May 25 Share #99 Posted May 25 I wonder when full 7 Exp service will resume? 0 Quote Link to comment Share on other sites More sharing options...
LGA Link N Train Posted May 26 Share #100 Posted May 26 On 5/25/2024 at 9:30 AM, T J Trainman said: I wonder when full 7 Exp service will resume? Whenever the contractors complete their work at Woodside-61st Street. 0 Quote Link to comment Share on other sites More sharing options...