Jump to content

Second Avenue Subway Discussion


CenSin

Recommended Posts


  • Replies 6.2k
  • Created
  • Last Reply

From the New York Daily News: 

 

MTA needs $66 Million to get Second Avenue Subway open on time.

 

Not really a surprise given how much work there still is to be done.

And that the new service pattern (with the (W)) would begin with the (Q) going to 57th, meaning its already past the start of the pick.

Edited by Eric B
Link to comment
Share on other sites

From the New York Daily News: 

 

MTA needs $66 Million to get Second Avenue Subway open on time.

 

Not really a surprise given how much work there still is to be done.

 

Board materials (page 128)

 

The MTA is also modifying the 63rd St station renovation contract to add more fire dampers and do maintenance work in the tunnels between Lex Av-63rd St and 57th St-7th Ave. 

 

Discussion: These retroactive modifications are for the furnishing and installation of 36 additional fire dampers and 6 motorized dampers in the duct work of the 63rd St./Lexington Avenue Station and the grouting/leak mitigation of the tunnel south of the 63rd St./Lexington Avenue Station to north of 57th Street and 7th Avenue Station. The contract calls for station reconstruction, as well as rehabilitation and reconstruction of new entrances to allow access from 3rd Avenue; connect new entrances to platforms; utility installation and relocation; and installation of elevators and escalators in the station and entrances.

 

Modification 165: NY State Building Code requires that fire dampers be installed in duct work passing through all fire-rated walls and floors in order to create fire separation. However, the contract documents do not indicate fire dampers at 36 such locations. Additionally, upon review of the station’s HVAC system, it was determined that 6 additional motorized dampers are necessary in order to properly control air flow throughout the station. This modification addresses the furnishing and installation of 36 fire dampers and 6 motorized dampers, each with access doors for maintenance purposes. Work includes demolition of cement block walls in order to enlarge openings, conduit relocation for access, removal and reinstallation of duct work and insulation, additional conduit, wire and associated electrical work to power the motorized dampers, sealing all openings around the modified duct work, furnishing and installation of two ceiling access panels where dampers are located above a finished ceiling and all associated surveying and shop drawing modifications. This modification is the result of an error in design.

 

It was necessary for this work to start immediately in order not to delay the turnover of the affected rooms to the Systems contractor. Approval to process this modification on a retroactive basis was obtained from the MTACC President on March 24, 2015. The Contractor’s proposal was $1,157,247; MTACC’s revised estimate is $985,884. Negotiations resulted in a lump sum price of $927,000, which is considered fair and reasonable. Savings of $230,247 were achieved.

 

Modification 262: The tracks in the tunnel south of the 63rd St./Lexington Avenue Station to north of 57th Street and 7th Avenue Station were built in the late 1970s as part of the "New Routes" 63rd St. Line. These tracks never had regular train service, and have been rarely used, except for occasional re-routes. Currently there is no scheduled revenue service over them however, this will change once SAS service begins with the ‘Q' train scheduled to operate along these tracks and continuing to the new 2nd Avenue Subway. Given the significant water ingress that has been constantly present in this area since its construction, the northbound and southbound tracks in this section have experienced severe degradation.

 

NYC Transit has determined that this tunnel section must be addressed immediately including the replacement of track, tunnel lighting, antenna cable, emergency alarms, emergency telephones, etc. The above track replacement and associated signal equipment work will be addressed through a third-party contract and NYC Transit in-house forces will address the remaining work, all of which must be completed in time for SAS Revenue Service. However, in order to perform this work, the water condition must be addressed first. NYC Transit has directed that the specialized chemical grout (NOH2O) and methods that were successfully employed on other MTACC and NYC Transit projects, be utilized in this tunnel section. Considering the proximity of the 63rd Street Station to this tunnel section, the fact that the grouting subcontractor and Judlau have collaborated on the previously successful NYC Transit applications and are currently performing grouting work in the station, it has been determined that the most expeditious way to address this leak mitigation work is by modification under Contract C-26006.

 

This modification addresses the development of grouting procedures, leak/crack inspections, preparation of concrete surfaces, drilling of grout holes, performance of pre-grouting water injection tests, injection of chemical grouting, patching all drill holes and providing safety, quality and administrative support. Funding for this modification will be provided by NYC Transit. In order to complete the work prior to the start of track work, it was necessary to start immediately.

 

The Contractor was directed to start the work on January 8, 2016. Approval to process this modification on a retroactive basis was subsequently obtained from the MTACC President on February 2, 2016. Additionally, the VP Materiel previously authorized partial payment to the contractor for work performed up to $650,000. The Contractor’s proposal was $6,310,113; MTACC’s revised estimate is $3,532,564. Negotiations resulted in a lump sum price of $3,750,000, which is considered fair and reasonable. Savings of $2,560,113 were achieved. The schedule impact of these modifications is still under review and any schedule adjustments will be addressed in a subsequent modification.

 

When it comes to the tunnels, you really can't help but wonder why the MTA didn't start this repair work until last month. It's not like this is an issue that just appeared out of nowhere one day, right?

Edited by Mysterious2train
Link to comment
Share on other sites

Yeah it will first BMT headed toward uptown Manhattan and The Bronx

I think you missed the point he was making.

 

What he means is that he's like to see Phase II complete before he's cadaverriffic or is too poor to live here.

Edited by LTA1992
Link to comment
Share on other sites

Bringing over from (W) train discussion:
 

I think that in the long term, stations at 125th St and 138th St / 149th St all need to be built to fully take advantage of the 2nd Avenue capacity. 125th St is probably being built first because it's the cheaper option, it is a universal transfer point, and it can enable the upper Lexington Ave line to be shut down for Fastrak. Plus, the 125th St subway will have to be built to improve crosstown travel in Uptown.

That will be needed for sure as well as the 125th Street crosstown that I would do that includes station stops at Lenox ( (2) / (3) ) and St. Nichols Avenue ( (A) / (B) / (C) / (D) ) before going to a terminal at Broadway-12th Avenue (transfer to (1) ) that I've said many times is needed, especially with by the time such is completed Columbia University's expansion likely complete. 

 

Link to comment
Share on other sites

 

Bringing over from (W) train discussion:

 

That will be needed for sure as well as the 125th Street crosstown that I would do that includes station stops at Lenox ( (2) / (3) ) and St. Nichols Avenue ( (A) / (B) / (C) / (D) ) before going to a terminal at Broadway-12th Avenue (transfer to (1) ) that I've said many times is needed, especially with by the time such is completed Columbia University's expansion likely complete. 

 

A 125th Street Cross town is nowhere near as important as replacing long gone service along Third Avenue, and providing long promised service to the East Bronx via Lafayette Avenue.

Link to comment
Share on other sites

A 125th Street Cross town is nowhere near as important as replacing long gone service along Third Avenue, and providing long promised service to the East Bronx via Lafayette Avenue.

That is true and I had noted my view in the (W) thread that the SAS Phase 2 should go to 149th/3rd Avenue in the Bronx with 138th Street (transfer to the (6) and 149th Street (transfer to (2) / (5) ), as I would do that with provisions to then run via the former 3rd Avenue El route (either as subway OR elevated, and if elevated with provisions to later if needed have such allow for a rebuild of the Manhattan 3rd Avenue El, even if that is unlikely to ever actually happen) to Gun Hill Road (and another transfer to the (2) / <5> ).  

Link to comment
Share on other sites

That is true and I had noted my view in the (W) thread that the SAS Phase 2 should go to 149th/3rd Avenue in the Bronx with 138th Street (transfer to the (6) and 149th Street (transfer to (2) / (5) ), as I would do that with provisions to then run via the former 3rd Avenue El route (either as subway OR elevated, and if elevated with provisions to later if needed have such allow for a rebuild of the Manhattan 3rd Avenue El, even if that is unlikely to ever actually happen) to Gun Hill Road (and another transfer to the (2) / <5> ).  

Why replace the old service with the same service when we could expand on that and send the line east via Webster and Allerton Avenues to Co-Op City? Also, unless a design that is quiet and beautiful that blends in with the cityscape is made, elevated lines will not make a return.

Link to comment
Share on other sites

Minor tidbits.

 

A 125th Street Cross town is nowhere near as important as replacing long gone service along Third Avenue, and providing long promised service to the East Bronx via Lafayette Avenue.

 

Realistically speaking, because of right-of-way, it would probably be cheaper to route an east Bronx rail line either along the Amtrak corridor or along the Bruckner.

 

Why replace the old service with the same service when we could expand on that and send the line east via Webster and Allerton Avenues to Co-Op City? Also, unless a design that is quiet and beautiful that blends in with the cityscape is made, elevated lines will not make a return.

 

Why as far north as Allerton? Pelham Pkwy is currently a far busier corridor that has lots of room for a right-of-way.

Link to comment
Share on other sites

Minor tidbits.

 

 

Realistically speaking, because of right-of-way, it would probably be cheaper to route an east Bronx rail line either along the Amtrak corridor or along the Bruckner.

 

 

Why as far north as Allerton? Pelham Pkwy is currently a far busier corridor that has lots of room for a right-of-way.

 

I would also have a Pelham Parkway route. Also, would the line be useful if it was on the Bruckner instead of on Lafayette Avenue?

Link to comment
Share on other sites

Join the conversation

You can post now and register later. If you have an account, sign in now to post with your account.

Guest
Reply to this topic...

×   Pasted as rich text.   Restore formatting

  Only 75 emoji are allowed.

×   Your link has been automatically embedded.   Display as a link instead

×   Your previous content has been restored.   Clear editor

×   You cannot paste images directly. Upload or insert images from URL.

×
×
  • Create New...

Important Information

By using this site, you agree to our Terms of Use.